Capital Campaign Update

July 2025

  • Specialized Roofing, the contractor for the Chapel and 1959 Roof repairs, has ordered supplies and applied for permits. Work on these projects will begin in August, starting with the Chapel roof.

  • We have submitted RFQs and are awaiting quotes on the Woburn Street exterior, lintels, and mortar repairs on the 1911 building. It’s not easy working on a vintage/antique building. Vinyl siding, anyone?

  • The Property Committee is researching new contractors to enlarge our pool of prospects for future projects. Having relationships with multiple vendors increases our knowledge and options, and enables us to make better decisions.

  • During the late summer or early fall, the Capital Campaign team will be reviewing where our campaign income stands regarding commitments. Again, thanks to all who have been able to stay current with their commitments.

Thank you,

The Capital Campaign Project Management Team